Suva Business District Load Shedding Schedule
There is a fault on our 33,000volts underground cable that supplies power from the Vatuwaqa Substation to the Suva Substation. This fault has affected power supply to the Suva Business District & suburbs. The EFL teams have been working on this fault since 2:00am on Wednesday morning. At this stage, it is not possible to estimate repair times, however EFL is working around the clock to locate and then repair the fault at the earliest possible time.
As mentioned yesterday, EFL has no other option but to resort to load shedding to ease the demand off the remaining healthy transmission circuits to avoid major unplanned blackouts. Our load shedding program for today (Thursday, 26th February 2015) is as follows:
Duration | Feeders | Areas Affected |
9.30am to 11.00am | Air Pacific | Air Pacific, Sukuna House, Kimberly Street, Good Enough Street, Credit Corporation, Desvouex Street, Berry Road, FTCU, Knolly Street, FTA Apartments, Victoria Park No.2, Tanoa Plaza Hotel, DC Complex, Korobasaqa House, Fineland Complex, Gordon St, Hinterland Complex, Marela House, Lynica House |
Walu Street | Walu Street, FM 96 Complex, Wahleys Complex, Walu Bay, Edinburgh House | |
Waimanu Road | Korea House, RB Patel, Waimanu Road | |
11.00am to 12.30pm | Eden Street | Belo Street, Dhanji Street, Howell Road Sub-division, Rewa Street, Armstrong Street, Alexander Street, Lekutu Street, Tawake Street, Grant Pl, Moti St, Bakshi St, Naqasima Pl, Eden Street, Flagstaff |
Reserve Bank | Reserve Bank, ANZ, Joske Street, Williams & Gosling, Foster Street, Life Insurance Corporation, BSP, Y.W.C.A, Civic Centre, Fiji Times, Vanua House, Civic Towers, Victoria Parade Sewerage | |
12.30pm to 2.00pm | MH Computer | MH Computers, Ellery St, Narseys Building, Honson Building, Dominion House, Harbour Centre, TFL Ganilau House, Village 6, Union Plaza, Westpac, Post Fiji, Renwick Road, Pier Street |
QE Drive | Queen Elizabeth Drive, Charlton Avenue, Nasese, FNU Catering School, Parliament Complex, Vuya Road, Pacific Theological College, Sukuna Road, Stoddart Street, USP, Battery Hill, Vudi Street, Muanikau Road, Sun Insurance Complex, Laucala Bay Road, Vesi Street | |
2.00pm to 3.30pm | Suva Central | MHCC, Suva Central |
Terry Walk | Mid City Plaza, Terry Walk, BP Building, Challenge Engineering, Robertson Road, MH Homemaker, Suva Market, Kasabias Complex, Kelton Investment, Wharf, Williams & Goslings | |
3.30pm to 5.00pm | Samabula | Ono Street, Moala Street, Lysaught, Footwear Export, Lakeba Street, LDS Temple |
High Street | New Maternity Hospital, Part of Waimanu Rd. from Samabula junction to Boron Rd., Grant Pl., Naqasima Pl., Part of Lekutu St., Toganivalu St. part of Mal St., part of Tawake St., Hedstrom Pl., Kasavu Rd. including Nauluvatu Sett., part of Princess Rd. from LDS Temple to FNU including Votua Rd. & Crompton Pl. | |
5.00pm to 6.30pm | Gordon Street | Gordon Street, Peninsula Hotel, Richards Road, Hamilton Beattie Street, Victoria Park, Forum Secretariat, Scotts Street, McGregor Rd, Bau Street, Pender Street, Knolly Street |
FEA wishes to thank all our valued customers who had assisted by operating their own stand-by
FEA wishes to thank all our valued customers who had assisted by operating their own stand-by generator sets independently to cater for their power requirements and request them to continue until we get the fault repaired.
Customers may experience intermittent power supply interruptions outside of the above stipulated time in the event of an unplanned event. However, EFL will endeavor to keep the power interruptions to a minimum.
The EFL sincerely apologizes for any inconvenience caused to all our valued customers which is beyond our control.
Hasmukh Patel
Chief Executive Officer