To establish the present level of customer satisfaction with regards to EFL’s Customer Services, EFL is conducting a customer satisfaction survey. Your views are important to us to make us improve our Customer Services and bring it to yet another level. It should not take you more than five minutes to answer the questions outlined below. As an appreciation of your commitment in answering these questions, EFL will give you a chance to go into the draw to win cash.

Wind Energy Projects

The Butoni Wind Farm

Wind Turbines at Butoni Wind Farm

 

This project was commissioned in 2008. With 37 Turbines (assuming average wind speeds of 5.47m/s) each generating a capacity of 275kW, for a combined total of approximately 10MW.

Statistics for the wind farm are given below since it commissioning in June 2007;

Total Generation Output = 38.7M units of electricity
Total Diesel Fuel Cost Savings = F$14.33M

Total Foreign Exchange Savings = F$8.71M
Total Diesel Fuel Saved = 8,144 tonnes of diesel
Total Emission Reduction = 25,301 tonnes of Carbon Dioxide